Are You Rumble Strip Ready? A General Contractor's Checklist
Rumble strips are generally the last item of work on a project,
and SPT can cut over 20 miles of asphalt in a single eight-hour shift.
This production speed catches many contractors by surprise.
Achieving our production potential translates into lower costs
for both of our companies. We request that your appropriate job site
employees review the following:
Schedule rumble strips when your project is in its final phase.
While most projects stipulate that all work must be completed in
project phases, every state DOT office has granted exceptions for
shoulder rumble strips. Most DOT's will allow rumble strips to be
completed under a single mobilization in the final phase, which
avoids multiple mobilization charges and having rumble strip
operations interfere with other work.
Paving and striping 100% complete. Scheduling paving or striping
simultaneously with the rumble strip operation usually interferes
with someone's work. Multiple mobilizations increase costs to the
general contractor.
Edgelines in place. SPT requests either a temporary or permanent
edgeline in place to begin construction. If we use asphalt joints,
edge of pavement, intermittent dots, or other references you increase
the risk that the rumble strips will not match final lines as required.
Brooms for cleanup. The general contractor handles sweeping on
most projects. If you plan to sweep the debris over the shoulder's
edge, you will need two brooms for shoulders over 6-feet wide, and
one broom for shoulders less than 6-feet. If the state requires you
to pick up the milling debris, two mechanical brooms and two dump
trucks are needed to keep up with milling operations. Vacuum brooms
do not work well picking up heavy millings at a three-mile per hour rate.
Traffic control. SPT will cut at a pace roughly 3 miles per hour
on asphalt. The general contractor should supply traffic control
to maintain that speed of operation. A moving operation lane closure works the best.
Water source. SPT will need 500 gallons of water once a day on
the job site. We cannot take water directly from a lake or stream.
|