 |
 |
 |
 |
| Main
Page > Project Design |
Specifications and Layout Considerations
| Costs and Benefits | What
Determines Price?
Is Retrofitting Really Less Expensive
Than Resurfacing? | Rolling Start
Dates |
Centerline & Secondary Road Rumble Strips | Rolled
vs. Milled
|
Rumble
Strip Construction: Retrofit Existing Shoulders or Wait Until
the Next Resurfacing?
Some
states, when initiating their rumble strip programs, made
a quick decision to add rumble strips to each resurfacing
project and left it at that. Today, however, most state department
of transportation offices have abandoned this incremental
installation of rumble strips. A typical rumble strip project
today will retrofit 300-1,500 shoulder miles of existing highway
shoulders with rumble strips (25 lane miles x 4 shoulders
= 100 shoulder miles).
There are three reasons state highway authorities have elected
to retrofit their existing shoulders with rumble strips rather
than wait until the next resurfacing:
-
Prevent hundreds or thousands more injuries and lost
lives versus the incremental benefits when done with
resurfacing. Most states can retrofit their entire interstate
systems with rumble strips in one or two years, instead
of the 10 or 15-year cycle necessary to resurface all
the shoulders in the state. That means rumble strips installed
as part of a large retrofit project will save lives 10
or 15 years sooner than if the state waited until all
its shoulders were resurfaced.
- Vastly
improve quality control. One or two inspectors can
carefully scrutinize a statewide retrofit project. This
allows for more manageable quality control versus 20 inspectors
overseeing 20 resurfacing projects each with different
contractors and subcontractors, in any given year. Nearly
all quality control failures on rumble strip projects
occur on resurfacing jobs, and not large, rumble strip
only projects.
-
Reduce Unit Costs by over 50%. The smaller the
project, the higher the unit costs. Taxpayers not only
pay twice as much as they should, but the high costs also
open the door for inefficient, makeshift rumble strip
mills that produce ineffective cuts or even damage highway
shoulders.
We
Have Finished Retrofitting Our Shoulders With Rumble Strips.
Now What?
Some states that have already retrofitted their existing
shoulders with rumble strips nonetheless have continued
their policy of not re-installing rumble strips as part
of resurfacing projects.
Instead of reinstalling the rumble strips as part of the
next resurfacing project, some states let a single statewide
project to construct rumble strips along all the highway
shoulders recently resurfaced throughout the state. This
way, states such as Connecticut that seen their unit costs
drop by half while eliminating their quality control problems
at the same time.
|
Back
to top
|
| Is
Retrofitting Really Less Expensive Than Resurfacing? |
On larger retrofit projects with 300 or more shoulder miles,
states can expect bids of $700/mile ($0.13/cut) or even less.
This unit price includes the construction, the clean up of
the debris, traffic control -- everything.
If your state currently includes rumble strips as part of
resurfacing projects, you may notice bid tab pricing as low
as $530 ($0.10/cut) or less. At first glance, your bid tabs
may indicate your state is paying the same or sometimes less
to construct rumble strips as part of resurfacing than it
would for a retrofit project. It isn't.
It is important to remember that typical bid tabs only reveal
the subcontractor pricing for cutting the rumble strips. To
this you must add incidental costs such as clean up of the
debris, traffic control, general contractor mark-up, etc.
Depending on clean up specifications, traffic control requirements,
and how the work is phased, these incidental costs can add
up to more than the construction costs. In this example below,
while the bid tabs may show a cost of $650 per mile for rumble
strips, the incidental costs that are added to other items
in the bid are more expensive than the milling of the
rumble strips:
|
 |
Click
here for a printable version of the illustration above.
|
Back
to top
|
| Rolling
Start Dates |
Many highway authorities use rolling start dates on their
construction projects, giving the contractor a 3-6 month window
to begin work. Once construction starts, the contractor is
held to a strict, uninterrupted construction schedule, usually
requiring 8-10 miles of cutting per day.
Most rumble strips contractors cut at a pace of about 10 miles
in an eight-hour day. With a single crew, a 400-mile rumble
strip project will take only 40 construction days to complete.
So while the construction quantities appear large, the construction
time is short.
Rolling start dates ensure the most competitive bidding for
the state. A relatively small number of rumble strip contractors
work on projects throughout the country. States that set a
specific start date risk choosing a date when few contractors
are available. Not only would this result in high prices,
but a state could find itself receiving bids only from inexperienced
contractors with untested equipment.
|
Back
to top
|
|
 |
|